[36799] in Hotline Meeting
Critical Shutdown Request - Bldg. 10 - 277 and 212 - 2/10
daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Fri Feb 7 12:49:01 1997
Date: Fri, 7 Feb 1997 12:45 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU, rrhonda@MIT.EDU
X-Envelope-To: rrhonda@mit.edu, shutdowns@mit.edu
X-Vms-To: IN%"shutdowns@mit.edu, rrhonda@mit.edu"
The following critical shutdown request for Bldg 10 - 277 and 212 for
2/10 is for your information and comment. Would you please let me know
if this has your approval or not.
Thank you.
Andrea Nichols
Operations Center
8-7872
Critical
Building: 10 - 277 and 212
System: Low pressure steam heating (only affects portion of
building with steam radiators)
Date: 2/10/97
Day: Monday
Time: 8:00 AM - 1:00 PM
Duration: 5 hours
Reason: Installation of new radiator control valve
Effect: Loss of low pressure (heating) steam