[36792] in Hotline Meeting
Shutdown Request - Bldg. 20B - 040 - 2/11
daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Fri Feb 7 09:34:14 1997
Date: Fri, 7 Feb 1997 09:30 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU, radams@mitlns.mit.edu, evans@tristan.mit.edu
X-Envelope-To: shutdowns@mit.edu
X-Vms-To: IN%"shutdowns@mit.edu, radams@mitlns.mit.edu, evans@tristan.mit.edu"
The following requested shutdown for Bldg. 20B -040 for 2/11 is for
your information and comment. Would you please let me know if this has
your approval or not.
Thanks.
Andrea Nichols
Operations Center
8-7872
Building: 20B - 040 (also 20B-043 and 20F Basement Wing)
System: Chill Water - 20B- 043 Fan coil unit and fan coil units plus
laser in 20F wing basement
Date: 2/11/97
Day: Tuesday
Time: 7:30 AM - 12:30 PM
Duration: 5 hours
Reason: Tie in three new fan coil units
Effect: Loss of chillled water and supply cooling air during
shutdown period.