[36764] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Filter Notification/Shutdown Request - Bldg. 26 - 152, 100,

daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Wed Feb 5 12:31:34 1997

Date: Wed, 5 Feb 1997 12:22 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: schedule@MIT.EDU, shutdowns@MIT.EDU, adams@MIT.EDU,
        gfp170@mitrlevm.mit.edu, blair@MIT.EDU
X-Envelope-To: adams@mit.edu, blair@mit.edu, schedule@mit.edu, shutdowns@mit.edu
X-Vms-To: 
 IN%"schedule@mit.edu, shutdowns@mit.edu, adams@mit.edu, gfp170@mitrlevm.mit.edu
   , blair@mit.edu"

The following filter change notification/shutdown request for Bldg. 26
- 152, 100, basement and trans. rm. for 2/6 is for your information and
comment. Would you please let me know if this has your approval or not.

Thank you.

Andrea Nichols
Operations Center
8-7872

Building:       26 - 152, 100, basement and trans. rm.
System:         Supply Fans, Air Handler 1, 2, 3 and 20
Date:           2/6/97
Day:            Thursday
Time:           7:00 AM - 2:00 PM
Duration:       Each unit will be down for 30 minutes for a total of 2
                hours within the above time frame.
Reason:         59 filter changes
Effect:         Loss of supply ventilation, cooling and/or heating for
                30 minutes per unit. While one unit is down, the others
                will remain operational.