Filter Change Notification - Bldg. 36 - 862DP and 012DP - 2/6/97

daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Wed Feb 5 11:30:21 1997

Date: Wed, 5 Feb 1997 11:26 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU, rroscoe@MIT.EDU, gfp170@mitrlevm.mit.edu
X-Envelope-To: rroscoe@mit.edu, shutdowns@mit.edu
X-Vms-To: IN%"shutdowns@mit.edu, rroscoe@mit.edu, gfp170@mitrlevm.mit.edu"

The following filter change notification for Bldg. 36 - 862DP and 012DP
for 2/6 is for your information and comment. If you have a concern
about this, please feel free to contact me.

Thank you.

Andrea Nichols
Operations Center/PM Office
8-7872

Building:       36 - 862DP and 012DP
System:         Fan Coil Units - PM#710822, 709715, 709716
Date:           2/6/97
Day:            Thursday
Time:           7:00 AM - 2:00 PM
Duration:       45 minutes within above time frame (each unit will take
                15 minutes to change filters)
Reason:         11 filter changes
Effect:         None - no units will be shut down during filter changes.