Filter change Advisory - Bldg. 6 - Flrs. 1 thru 4 -- 2/4/97

daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Mon Feb 3 14:14:48 1997

Date: Mon, 3 Feb 1997 13:21 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: schedule@MIT.EDU, shutdowns@MIT.EDU, radams@mitlns.mit.edu, mbj@MIT.EDU,
        acherron@MIT.EDU, edc@MIT.EDU, elp@MIT.EDU, farideh@MIT.EDU
X-Envelope-To: acherron@mit.edu, edc@mit.edu, elp@mit.edu, farideh@mit.edu,
 mbj@mit.edu, schedule@mit.edu, shutdowns@mit.edu
X-Vms-To: 
 IN%"schedule@mit.edu, shutdowns@mit.edu, radams@mitlns.mit.edu, mbj@mit.edu, ac
   herron@mit.edu, edc@mit.edu, elp@mit.edu, farideh@mit.edu"

The following filter change advisory for Bldg. 6 floors 1 thru 4 for
2/4 is for your information and comment. If you have a concern, please
feel free to contact me.

Thank you.

Andrea Nichols
Operations Center/PM Office
8-7872

Building:       6 - floors 1 thru 4
System:         Air Handler 2 (PM#703284)
Date:           2/4/97
Day:            Tuesday
Time:           8:00 AM - 2:00 PM
Duration:       15 minutes within the above time frame
Reason:         6 filter changes
Effect:         None - no equipment will be shut down during filter
                changes.