[36688] in Hotline Meeting
Requested Shutdown - Bldg. 9 - 2/3/97
daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Fri Jan 31 09:13:20 1997
Date: Fri, 31 Jan 1997 08:48 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU, jobrien@MIT.EDU, westlunc@MIT.EDU, pcollymo@MIT.EDU,
roneil@MIT.EDU
X-Envelope-To: jobrien@mit.edu, pcollymo@mit.edu, roneil@mit.edu,
shutdowns@mit.edu, westlunc@mit.edu
X-Vms-To:
IN%"shutdowns@mit.edu, jobrien@mit.edu, westlunc@mit.edu, pcollymo@mit.edu, ron
eil@mit.edu"
The following requested shutdown for Bldg. 9 for 2/3 is for your
information and comment. Would you please let me know if this has your
approval or not.
Thank you.
Andrea Nichols
Operations center
8-7872
Building: 9 - 3rd floor (but will also affect entire bldg.)
System: Chilled Water
Date: 2/3/97
Day: Monday
Time: 7:30 AM - 3:30 PM
Duration: 8 hours
Reason: Tie in new fan coil unit which serves Rms. 550, 551, 552,
basement cooling but affects entire fan coil units in building
(chilled water/air conditioning)
Effect: Loss of chilled water (air conditioning) during
shutdown period.