Filter Change Notification/Shutdown - Bldg. E23 - 1/30/97

daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Wed Jan 29 11:07:52 1997

Date: Wed, 29 Jan 1997 11:02 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU, roge@med.mit.edu, edwa@med.mit.edu, andrea@wccf.mit.edu,
        bengel@MIT.EDU
X-Envelope-To: bengel@mit.edu, shutdowns@mit.edu
X-Vms-To: 
 IN%"shutdowns@mit.edu, roge@med.mit.edu, edwa@med.mit.edu, andrea@wccf.mit.edu,
    bengel@mit.edu"

The following filter change advisory/shutdown for E23 for 1/30 is for
your review and comment. Would you please let me know if you have a
concern about this.

Thanks.

Andrea Nichols
Operations Center/PM Office
8-7872

Building:       E23 - PM#707704/AH 11 -Basement thru 5th flrs; AH10
                (PM#707703) 1st & 4th floors; AH8 (PM#707701) 1st,
                2nd & 3rd floor South; AH9 (PM707702) floors 1 - 4
System:         Air Handlers/ Supply Fans for ventilation, cooling and
                heating
Date:           1/30/97
Day:            Thursday
Time:           7:00 AM - 2:00 PM
Duration:       7 hours
Reason:         73 Filter change
Effect:         Minimal - each supply fan will be down one at a time
                for 30 minutes while the others will remain operational.