[36600] in Hotline Meeting
Requested Shutdown - Bldg. E15 - 1/31/97
daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Fri Jan 24 11:06:28 1997
Date: Fri, 24 Jan 1997 11:03 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU, opsnote@MIT.EDU
X-Envelope-To: opsnote@mit.edu, shutdowns@mit.edu
X-Vms-To: IN%"shutdowns@mit.edu, opsnote@mit.edu"
The following requested shutdown for Bldg. E15 for 1/31 is for your
information and comment. Would you please let me know if this has your
approval or not.
FYI --Greg Tucker, facilities manager of Bldg. E15 has approved this work.
Thanks.
Andrea Nichols
Operations Center
8-7872
Building: E15
System: Emergency Power, access controls, elevators, partial
corridors/stairs and paging system
Date: 1/31/97
Day: Friday
Time: 6:00 AM - 6:10 AM
Duration: 10 minutes
Reason: To replace faulty circuit breaker that feeds one
passenger elevator.
Effect: Loss of access controls, emergency power, elevators,
partial corridors/stairs & paging system.