Shutdown Request - Bldg. 18 - all rooms - 1/25/97

daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Thu Jan 23 12:11:53 1997

Date: Thu, 23 Jan 1997 11:56 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU, opsnote@MIT.EDU, mbj@MIT.EDU
X-Envelope-To: mbj@mit.edu, opsnote@mit.edu, shutdowns@mit.edu
X-Vms-To: IN%"shutdowns@mit.edu, opsnote@mit.edu, mbj@mit.edu"

The following shutdown request for Bldg. 18 - for 1/25 is for your
information and comment. Would you please let me know if this has your
approval or not.

Thank you.

Andrea Nichols
Operations Center
8-7872

Building:       18 - all rooms including restroom facilities, drinking
                fountains, kitchen and lab sinks
System:         All domestic and de-ionized water (hot and cold)
Date:           1/25/97
Day:            Saturday
Time:           6:00 AM - 2:00 PM
Duration:       8 hours
Reason:         Change all valves for both systems
Effect:         Loss of pure, hot domestic, hot lab process, cold domestic,
                cold lab process and de-ionized water.