Requested Critical Shutdown - Bldg. 4 - 430, 440, 444, 454, 460, 469,

daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Tue Jan 21 09:04:47 1997

Date: Tue, 21 Jan 1997 09:02 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU, mbj@MIT.EDU
X-Envelope-To: mbj@mit.edu, shutdowns@mit.edu
X-Vms-To: IN%"shutdowns@mit.edu, mbj@mit.edu"

The following Critical Shutdown Request for Bldg. 4 (see rooms listed
below) for 1/22/97 is for your information and comment. Would you please
let me know if this has your approval or not.

Thanks very much.

Andrea Nichols
Operations Center
8-7872

Critical
Building:       4-430, 440, 444, 454, 460, 469, 471, 472, 470 & 474
System:         Non-potable (lab process) hot and cold water;
                also cold water supply to r.o. system in 4-429 and
                smoke detector in 4-429
Date:           1/22/97
Day:            Wednesday
Time:           7:00 AM - 12 Noon
Duration:       5 hours
Reason:         Two leaks on non-potable cold water pipe
Effect:         Loss of hot and cold lab process water and fire alarm
                system