[36476] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Requested Shutdown - Bldg. 8-102 and 106 - 1/16/97

daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Wed Jan 15 10:05:39 1997

Date: Wed, 15 Jan 1997 10:01 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU, acherron@MIT.EDU
X-Envelope-To: acherron@mit.edu, shutdowns@mit.edu
X-Vms-To: IN%"shutdowns@mit.edu, acherron@mit.edu"

The following shutdown request for Bldg. 8-102 and 106 for 1/16/97 is
for your information and comment. Would you please let me know if this
has your approval or not.

Thank you.

Andrea Nichols
Operations Center
8-7872

Building:       8-102 (106 room where tie-in to be made)
System:         Chilled water, heating steam
Date:           1/16/97
Day:            Thursday
Time:           8:00 AM - 12 noon
Duration:       4 hours
Reason:         Tie in Fan Coil Unit to Chilled Water, controls
                for heating steam.
Effect:         Loss of chilled water, supply cooling and supply
                heating during shutdown period as follows:

                Loss of chilled water for 102 and 106, heat for hitemp
                materials processing technologies

home help back first fref pref prev next nref lref last post