[36347] in Hotline Meeting
Requested Shutdown - Bldg. 38 - South Offices,
daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Fri Jan 3 15:46:27 1997
Date: Fri, 3 Jan 1997 15:44 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU, gfp170@mitrlevm.mit.edu, schedule@MIT.EDU,
rroscoe@MIT.EDU, shawn@eddie.mit.edu, devries@MIT.EDU
X-Envelope-To: devries@mit.edu, rroscoe@mit.edu, schedule@mit.edu,
shutdowns@mit.edu
X-Vms-To:
IN%"shutdowns@mit.edu, gfp170@mitrlevm.mit.edu, schedule@mit.edu, rroscoe@mit.e
du, shawn@eddie.mit.edu, devries@mit.edu"
The following requested shutdown for Bldg. 38 - South Ofices - Floors
1-6 for anywhere from 1/13 to 1/31 is for your information and review.
As you will see, the date, time is up to you. Physical Plant folks can
come in over the weekend, begin work at 4:00 AM or from 11:00 PM to the
next morning. It is up to you and we would most appreciate your
suggestion.
Please advise and thank you.
Andrea Nichols
Operations Center
8-7872
Building: 38 - South Offices - Floors 1-6
System: Supply ventilation, cooling and heating
PM#701939 - Supply Fan/Air Handler 3 A & B
PM#701994 - Return Fan 3
Date: Between 1/13 and 1/31
Day: See Above
Time: Anytime days, evenings, or weekends
Duration: 4 - 6 hours
Reason: Replace bearings for Return Fan #3
Effect: Loss of supply ventilation, cooling and heating
Please note: Physical Plant needs 5 day's notice
based on scheduled date to set up. Confined space
entry permit required.