[36276] in Hotline Meeting
Requested Shutdown - Bldg. 18 - Entire Bldg. - 12/26
daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Fri Dec 20 16:12:52 1996
Date: Fri, 20 Dec 1996 16:11 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU, manolis@MIT.EDU
X-Envelope-To: manolis@mit.edu, shutdowns@mit.edu
X-Vms-To: IN%"shutdowns@mit.edu, manolis@mit.edu"
The following requested shutdown for Bldg. 18 for 12/26/96 is for your
information and comment. Would you please pass this along to Karen
Warren for her handling.
Thanks Melissa and Happy Holidays to you!
Andrea Nichols
Operations Center
8-7872
Building: 18
System: City Water
Date: 12/26/96
Day: Thursday
Time: 3:00 PM to 10:00 PM
Duration: 7 hours
Reason: Tie-in of backflow preventers to protect City water
main.
Effect: Loss of hot domestic and hot lab process water, cold domestic
and cold lab process water; compressed lab air, lab
vacuum air, lab waste, sanitary and storm drain drainage as
well as the Harris Rooms.