Shutdown Request - Bldgs. E23 and E25 - 1/11 & 12/96

daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Wed Dec 18 09:08:25 1996

Date: Wed, 18 Dec 1996 09:06 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU, roge@med.mit.edu, cobb@ai.mit.edu, schedule@MIT.EDU,
        jmganno@MIT.EDU, placido@MIT.EDU, kjallen@MIT.EDU, gengel@MIT.EDU,
        andrea@wccf.mit.edu, cac@MIT.EDU, scotts@mitvma.mit.edu,
        pbrown@MIT.EDU, jcy@imager.mit.edu
X-Envelope-To: cac@mit.edu, gengel@mit.edu, jmganno@mit.edu, kjallen@mit.edu,
 pbrown@mit.edu, placido@mit.edu, schedule@mit.edu, shutdowns@mit.edu
X-Vms-To: 
 IN%"shutdowns@mit.edu, roge@med.mit.edu, cobb@ai.mit.edu, schedule@mit.edu, jmg
   anno@mit.edu, placido@mit.edu, kjallen@mit.edu, gengel@mit.edu, andrea@wccf.m
   it.edu, cac@mit.edu, scotts@mitvma.mit.edu, pbrown@mit.edu, jcy@imager.mit.ed
   u"

The following shutdown request for Bldgs. E23 and E25 for 1/11 and 1/12
is for your information and comment. Would you please let me know if
this has your approval or not.

Thanks very much.

Andrea Nichols
Operations Center
8-7872

Building:       E23 and E25
System:         All cold and hot domestic and lab process water
Date:           1/11 and 1/12/96
Day:            Saturday and Sunday
Time:           4:00 PM - 12 midnight each day
Duration:       8 hours each day for 2 days
Reason:         To check domestic water for cross connections
Effect:         Loss of hot domestic water, hot lab process water, heating hot
                water, cold domestic and cold lab process water. This
                will also affect compressed lab air and lab vacuum air.