[36066] in Hotline Meeting
Requested Critical Shutdown - Bldg. W20 - 12/7/96
daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Thu Dec 5 10:35:20 1996
Date: Thu, 5 Dec 1996 09:46 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU, mwf@MIT.EDU
X-Envelope-To: mwf@mit.edu, shutdowns@mit.edu
X-Vms-To: IN%"shutdowns@mit.edu, mwf@mit.edu"
The following critical shutdown request for W20 for 12/7 is for your
information and comment. Would you please let me know if this has your
approval or not.
Thanks very much.
Andrea Nichols
Operations Center
8-7872
Building: W20 - 5th Floor East & 5th Floor Athena Room
System: Air Handler 9
Date: 12/7/96
Day: Saturday
Time: 6:00 AM - 2:00 PM
Duration: 8 hours
Reason: Repair reheat and preheat coils
Effect: Loss of supply ventilation, cooling and heating during
shutdown period.