Requested Critical Shutdown - Bldg. W20 - 12/7/96

daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Thu Dec 5 10:35:20 1996

Date: Thu, 5 Dec 1996 09:46 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU, mwf@MIT.EDU
X-Envelope-To: mwf@mit.edu, shutdowns@mit.edu
X-Vms-To: IN%"shutdowns@mit.edu, mwf@mit.edu"

The following critical shutdown request for W20 for 12/7 is for your
information and comment. Would you please let me know if this has your
approval or not.

Thanks very much.

Andrea Nichols
Operations Center
8-7872

Building:       W20 - 5th Floor East & 5th Floor Athena Room
System:         Air Handler 9
Date:           12/7/96
Day:            Saturday
Time:           6:00 AM - 2:00 PM
Duration:       8 hours
Reason:         Repair reheat and preheat coils
Effect:         Loss of supply ventilation, cooling and heating during
                shutdown period.