Requested Electrical Shutdown - Bldg. 13 - 1/6/97

daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Thu Nov 28 14:41:48 1996

Date: Thu, 28 Nov 1996 14:40 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU, schedule@MIT.EDU, cus-coach@MIT.EDU
X-Envelope-To: cus-coach@mit.edu, schedule@mit.edu, shutdowns@mit.edu
X-Vms-To: IN%"shutdowns@mit.edu, schedule@mit.edu, cus-coach@mit.edu"

The following requested electrical shutdown for Bldg. 13 for 1/6/97 is
for your review and comment. Would you please let me know if this has
your approval.

Thanks very much.

Andrea Nichols
Operations Center
8-7872

Building:       13
System:         Normal Electrical power (emergency power not affected)
Date:           1/6/97
Day:            Monday
Time:           4:30 AM - 7:30 AM
Duration:       3 hours
Reason:         High voltage distribution upgrade
Effect:         Loss of access controls, building power, computers,
                lighting, chilled, pure, heating hot water and de-ionized
                water, supply ventilation, cooling, heating, exhaust
                laboratory, exhaust general, exhaust-toilet, compressed
                control, compressed lab and lab vacuum air.

                A 3-hour outage will mitigate future shutdowns.