[35386] in Hotline Meeting
Requested Shutdown - Certain Rooms - Bldg. E40 - 10/23
daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Tue Oct 22 09:06:17 1996
Date: Tue, 22 Oct 1996 08:59 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU, jfob@MIT.EDU, fairfld@MIT.EDU
X-Envelope-To: fairfld@mit.edu, jfob@mit.edu, shutdowns@mit.edu
X-Vms-To: IN%"shutdowns@mit.edu, jfob@mit.edu, fairfld@mit.edu"
The following which pertains to the requested shutdown of certain rooms
in E40 for 10/23/96 is for your review and information. Would you
please let me know if this shutdown is acceptable or unacceptable.
Thank you.
Andrea Nichols
Operations Center
8-7872
Building: E40 - 479, 471, 429, 433, 319PA, 333PA, 419, 409,
391PA, 379PA, 465 and 453
System: Fan Coil Units
Date: 10/23/96
Day: Wednesday
Time: 9:00 AM - 9:45 AM
Duration: 45 minutes
Reason: Filter change
Effect: Minimal - this will affect the supply cooling and
supply heating, but each unit will be down for approx. 5
minutes while the filter is being changed.
It is also requested that if there is any equipment or
desks with papers next to or beneath a unit that the
equipment be moved (or at least covered) and any paperwork be
removed from desks so that workmen can easily access the units.