[35371] in Hotline Meeting
Requested Shutdown - Bldg. E51 - 10/25/96
daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Mon Oct 21 16:36:00 1996
Date: Mon, 21 Oct 1996 16:28 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU, schedule@MIT.EDU, mmarshal@MIT.EDU, lhill@MIT.EDU,
mdimauro@MIT.EDU, dlbrooks@MIT.EDU, jstein@mitvma.mit.edu
X-Envelope-To: dlbrooks@mit.edu, lhill@mit.edu, mdimauro@mit.edu,
mmarshal@mit.edu, schedule@mit.edu, shutdowns@mit.edu
X-Vms-To:
IN%"shutdowns@mit.edu, schedule@mit.edu, mmarshal@mit.edu, lhill@mit.edu, mdima
uro@mit.edu, dlbrooks@mit.edu, jstein@mitvma.mit.edu"
The following information which pertains to the requested shutdown for
Bldg. E51 is for your information and review. Would you please let me
know if this is acceptable or unacceptable.
Thanks very much.
Andrea Nichols
Operations Center
8-7872
Building: E51 - West Half of Bldg. & East Half of old Bldg.
System: Supply Fan/Air Handler 1 - PM#707101 and
Supply Fan/Air Handler 2 - PM#707103
Date: 10/25/96
Day: Friday
Time: 9:00 AM - 10:00 AM
Duration: 1 hour
Reason: Filter changes
Effect: Loss of supply ventilation, supply cooling and supply
heating. - Each Supply Fan/Air Handler will be down for
30 minutes only.