Requested Shutdown - Bldg. 26 Basement - 10/22/96
daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Mon Oct 21 09:30:38 1996
Date: Mon, 21 Oct 1996 09:23 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU, adams@mitlns.mit.edu, gfp170@mitrlevm.mit.edu,
blair@mitvma.mit.edu
X-Envelope-To: shutdowns@mit.edu
X-Vms-To:
IN%"shutdowns@mit.edu, adams@mitlns.mit.edu, gfp170@mitrlevm.mit.edu, blair@mit
vma.mit.edu"
The following requested shutdown for Bldg. 26 (basement) for 10/22 is
for your review and informaton. Would you please let me know if this
has your approval or disapproval.
Thank you.
Andrea Nichols
Operations Center
8-7872
Building: 26 (Basement)
System: Air Handler 2 - PM#701625 located in 26-004
Date: 10/22/96
Day: Tuesday
Time: 8:00 AM - 9:00 AM (30 minutes between this time frame)
Duration: 30 minutes
Reason: Filter Change
Effect: Loss of supply ventilation during 30 minute shutdown.