Requested Shutdown - Bldg. NW13-206, 204 & 133 - 10/14-15/96

daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Thu Oct 10 13:11:02 1996

Date: Thu, 10 Oct 1996 12:19 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU, d-zone@MIT.EDU, devries@MIT.EDU
X-Envelope-To: d-zone@mit.edu, devries@mit.edu, shutdowns@mit.edu
X-Vms-To: IN%"shutdowns@mit.edu, d-zone@mit.edu, devries@mit.edu"

The following requested shutdown request for Bldg. NW13-206, 204
and 133 for 10/14-15 is for your information and review. Would you
please let me know if this shutdown is acceptable or unacceptable.

Thanks very much.

Andrea Nichols
Operations Center
8-6651

Building:       NW13-206, 204 & 133
System:         Fan Supply - PM#704048 (206); #704050 (204); and
                #703959 (133)
Date:           10/14 PM - 10/15 AM
Day:            Monday PM - Tuesday AM
Time:           11:00 PM (Mon.) - 7:00 AM (Tues.)
Duration:       8 hours
Reason:         Preventive maintenance
Effect:         Minimal - supply ventilation - each supply fan will be
                down for 1 hour.