[35154] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Requested Shutdown - Bldgs. E53 and E56 - 10/13-14/96

daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Mon Oct 7 17:38:25 1996

Date: Mon, 7 Oct 1996 14:01 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU, mmarshal@MIT.EDU, lhill@MIT.EDU, allison@MIT.EDU,
        ruggere@MIT.EDU
X-Envelope-To: allison@mit.edu, lhill@mit.edu, mmarshal@mit.edu,
 ruggere@mit.edu, shutdowns@mit.edu
X-Vms-To: 
 IN%"shutdowns@mit.edu, mmarshal@mit.edu, lhill@mit.edu, allison@mit.edu, rugger
   e@mit.edu"

The following which pertains to the requested shutdown for Bldgs. E53
and E56 for 10/13 & 14 is for your information and review. Would you
please let me know if this shutdown is acceptable or unacceptable.

Thanks very much.

Andrea Nichols
Operations Center
8-6651

Buildings:      E53 and E56 - all restroom facilities
System:         Potable hot and cold water
Date:           10/13 and 14
Day:            Sunday and Monday
Time:           7:00 AM - 4:00 PM each day
Duration:       48 hours (potable hot and cold water will remain shut
                off overnight)
Reason:         Replace 8" main gate valve coming into buildings.
Effect:         Shutdown of hot and cold domestic water for 48
                hours--no restrooms will be operational in these two buildings.
                This will also affect the sanitary draingage system
                during shutdown period.

home help back first fref pref prev next nref lref last post