[34945] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Requested Shutdown - Bldg. 14N (323)

daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Tue Sep 24 16:16:30 1996

Date: Tue, 24 Sep 1996 14:30 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU
X-Envelope-To: shutdowns@mit.edu
X-Vms-To: IN%"shutdowns@mit.edu"

The following information which pertains to the requested shutdown for
Bldg. 14N 323 is for your review. Would you please let me know if this
would be either acceptable or unacceptable.

Thank you.

Andrea Nichols
Operations Center
8-6651

Building:       14N 323 (Foreign Languages & Literature)
System:         Asbestos removal notice
Date:           9/27/96
Day:            Friday
Time:           4:00 PM - 12 midnight
Duration:       8 hours
Reason:         To remove asbestos tile from entire room--occupants of
                this room will have to vacate it during shutdown period.
Effect:         None - asbestos removal.


home help back first fref pref prev next nref lref last post