[34536] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Requested Shutdowns

daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Thu Aug 29 13:40:33 1996

Date: Thu, 29 Aug 1996 13:35 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU, schedule@MIT.EDU, relices@MIT.EDU, karensal@MIT.EDU,
        blair@mitvma.mit.edu, lindlore@MIT.EDU, jfucillo@MIT.EDU,
        shyoung@MIT.EDU
X-Envelope-To: jfucillo@mit.edu, karensal@mit.edu, lindlore@mit.edu,
 relices@mit.edu, schedule@mit.edu, shutdowns@mit.edu, shyoung@mit.edu
X-Vms-To: 
 IN%"shutdowns@mit.edu, schedule@mit.edu, relices@mit.edu, karensal@mit.edu, bla
   ir@mitvma.mit.edu, lindlore@mit.edu, jfucillo@mit.edu, shyoung@mit.edu"

The following requestd shutdowns are for your information and review.
Would you please let me know if these have your approval or disapproval
at your earliest convenience.

Thanks very much.

Andrea Nichols
Operations Center
8-6651

Building:       56, 66, 54 and 68
System:         Lab and control air
Date:           9/3/96
Day:            Tuesday
Time:           7:00 AM - 9:00 AM
Duration:       1 hours (one hour between 7 and 9 AM)
Reason:         Tie in new compressor
Effect:         Minimal- all systems have backup up compressed control
                and compressed lab air except for Bldg. 68 lab air.
                There is no lab compressed air for Bldg. 68.
                There will be no impact on Biemann's Lab.

Building:       16, Basement, floors 1 & 2 & Biemann's Labs (Bldg. 56)
System:         Chilled water supply and return
Date:           9/7/96
Day:            Saturday
Time:           6:00 AM - 2:00 PM
Duration:       8 hours
Reason:         Tie in new supply and return on 1st and 2nd floors
Effect:         No chilled water supply and return until new system
                tied in.


home help back first fref pref prev next nref lref last post