Requested Critical Shutdown - Bldg. 1 - 8/21/96

daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Mon Aug 19 08:57:22 1996

Date: Mon, 19 Aug 1996 08:52 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU, mgibson@MIT.EDU, mamullow@MIT.EDU,
        tkaalst@mitvma.mit.edu
X-Envelope-To: mamullow@mit.edu, mgibson@mit.edu, shutdowns@mit.edu
X-Vms-To: 
 IN%"shutdowns@mit.edu, mgibson@mit.edu, mamullow@mit.edu, tkaalst@mitvma.mit.ed
   u"

The following information which pertains to the requested critical
shutdown of certain rooms in Building 1 is for your review. Would you
please let me know if this is either acceptable or unacceptable.

Thanks very much.

Andrea Nichols
Operations Center
8-6651

Building:       1-131, 133, 033, 025, 123, 125, 229, and 225
System:         Chilled Water/air conditioning
Date:           8/21/96
Day:            Wednesday
Time:           8:00 AM - 2:00 PM
Duration:       6 hours
Reason:         Have to tie in new chilled water fan coil units
Effect:         Loss of chilled water, no air conditioning during
                shutdown.