Requested Shutdowns - Bldg. 13

daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Fri Aug 16 10:48:18 1996

Date: Fri, 16 Aug 1996 10:43 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU, dhenry5@MIT.EDU
X-Envelope-To: dhenry5@mit.edu, shutdowns@mit.edu
X-Vms-To: IN%"shutdowns@mit.edu, dhenry5@mit.edu"

The following information which pertains to Building 13 requested
shutdowns is for your review. Would you please let me know if these
have your approval or disapproval at your earliest convenience.

Thanks very much.

Andrea Nichols
Operations Center
8-6651

Building:       13 - 1026 and 1029
System:         Exhaust Laboratory Hoods and stack extensions -
                PM# 701093 and 701092
Date:           8/20 and 8/21/96
Day:            Tuesday and Wednesday
Time:           7:00 AM - 8/20 - 4:00 PM 8/21
Duration:       2 days
Reason:         Reroofing Building 13, temporary relocation of
                exhaust laboratory hood fans and stack extentions.
Effect:         Loss of exhaust laboratory hood fans

Building:       13 - 5155A, Fan Room "H", 5148, 4148 and 4151
System:         Laboratory Exhaust Hood Fans - PM#701821, #701822 and
                #701823
Date:           8/21/96
Day:            Wednesday
Time:           7:00 AM - 12 Noon (more or less)
Duration:       5 hours (more or less)
Reason:         Reroofing Building 13 - relocating stack extensions
Effect:         Loss of laboratory exhaust hood fans

Building:       13-3035, 5027 and 3035 (PM#715146, #714625, #715147 and
                #713553)
System:         Fan Exhaust Hoods #2 and 3, General Exhaust Fans and
                cold domestic water in Rm. 5027 (Perchloric Acid) - PM#714625
                only)
Date:           8/21 and 8/22
Day:            Wednesday and Thursday
Time:           7:00 AM (8/21) - 4:00 PM more or less on 8/22
Duration:       2 days
Reason:         Reroofing Building 13 - temporary relocation of
                Fan Exhaust Hoods, General Exhaust Fans and stack
                extensions.
Effect:         Loss of laboratory fan exhaust hoods, general
                exhaust fans and cold domestic water (Room 5027 only -
                PM#714625 - Perchloric Acid)

Building:       13-5060
System:         General Exhaust Fan (PM#714366)
Date:           8/22 - 8/23/96
Day:            Thursday and Friday
Time:           7:00 AM (8/22) - 4:00 PM (more or less on 8/23)
Duration:       2 days
Reason:         Reroofing Building 13 - temporary relocation of General
                Exhaust Fans and Stack Extensions
Effect:         Loss of general exhaust fans