[34316] in Hotline Meeting
Requested Shutdown - Bldg. 13 - 8/19/96
daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Mon Aug 12 12:59:17 1996
Date: Mon, 12 Aug 1996 12:54 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU
X-Envelope-To: shutdowns@mit.edu
X-Vms-To: IN%"shutdowns@mit.edu"
The following information which pertains to the requested shutdown of
Building 13 for Monday, 8/19 is for your review. Would you please let
me know if this shutdown is either acceptable or unacceptable.
Thanks for your help.
Andrea Nichols
Operations Center
8-6651 or via return
e-mail
Building: 13 - 5135 (Fan Room G)
System: Fan Exhaust Hoods and General Exhaust Fans
Date: 8/19/96
Day: Monday
Time: 7:00 AM - 12 Noon (more or less)
Duration: 5 hours (more or less)
Reason: Re-roofing Building 13
Effect: Loss of fan exhaust hoods and General Exhaust Fans in the
following rooms:
Preventive Maintenancce # Room No.
701751 13-3143
701752 4123
701753 4135
701754 3135
701755 3124
701757 3136
701756 4139
701768 5128
701748 2132
701746 4139
701745 3144
701744 4139
701743 4139