[34242] in Hotline Meeting
Requested Shutdown - Bldg. 39
daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Mon Aug 5 12:03:57 1996
Date: Mon, 5 Aug 1996 11:59 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU, mcgrath@mtl.mit.edu
X-Envelope-To: shutdowns@mit.edu
X-Vms-To: IN%"shutdowns@mit.edu, mcgrath@mtl.mit.edu"
The following information which pertins to the requested shutdown of
Building 39 is for your review. Would you please advise if this is
either acceptable or unacceptable at your earliest convenience.
Thanks very much
Andrea Nichols
Operations Center
8-6651
Building: 39-287, 412, 403, 430A and 412 (Hood)
System: Fan Supply and Fan Hood
Date: 8/7 PM - 8/8 AM
Day: Wednesday (PM) - Thursday (AM)
Time: 11:00 PM (Wed.) - 7:00 AM (Thurs.)
Duration: 8 hours
Reason: Preventive Maintenance Work
Effect: Loss of Fan Supply and Fan Hood (down one at a time for
one hour each) as follows:
PM#707539 - Room # 39-287; PM#708474 - Room #39-412;
PM#708635 - Room #39-412; PM#708475 - Room #39-403;
PM# 708471 and #708470 - Room 39-430A