[34220] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Requested Shutdown - Bldg. 54 - North Zone

daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Fri Aug 2 09:15:06 1996

Date: Fri, 2 Aug 1996 09:11 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU, schedule@MIT.EDU, relices@MIT.EDU
X-Envelope-To: relices@mit.edu, schedule@mit.edu, shutdowns@mit.edu
X-Vms-To: IN%"shutdowns@mit.edu, schedule@mit.edu, relices@mit.edu"

The following materials which pertain to the requested shutdown of
Building 54-North is for your review and information.  Would you
please let me know if this shutdown is either acceptable or
unacceptable.

Thanks very much.

Andrea Nichols
8-6651 or return e-mail

Building:       54 North Zone
System:         Fan Supply - Air Handler 1
Date:           8/7/96
Day:            Wednesday
Time:           8:00 AM - 3:00 PM
Duration:       7 hours
Reason:         Repair suction flex connection on AH-1
Effect:         Loss of supply ventilation. Example of North Zone Rooms
                would be 425 to 411; 527A to 533, etc.