Requested Shutdown - Bldg. 31 - 8/2/96

daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Wed Jul 31 13:50:19 1996

Date: Wed, 31 Jul 1996 13:43 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU, lindlore@MIT.EDU, magowen@MIT.EDU, pmccosco@MIT.EDU
X-Envelope-To: lindlore@mit.edu, magowen@mit.edu, pmccosco@mit.edu,
 shutdowns@mit.edu
X-Vms-To: 
 IN%"shutdowns@mit.edu, lindlore@mit.edu, magowen@mit.edu, pmccosco@mit.edu"

The material below which pertains to the requested shutdown for
Building 31 is for your review and information. Would you please let me
know if this has your approval or disapproval.  I can be contacted via
return e-mail or at 8-6651.

Thanks for your help.

Andrea Nichols
Operations Center

Building:       31 - rooms 210 through 237 - rooms 049 through 058,
                rooms 230 - 233 already off.
System:         Chill water
Date:           8/2/96
Day:            Friday
Time:           7:30 AM - 1:30 PM
Duration:       6 hours
Reason:         Have to tie in new Fan Coil Unit.
Effect:         Loss of cooling (or chillwater) in rooms 210 through
                237; loss of chilled water (no cooling) in Rooms 049 - 058