[34137] in Hotline Meeting
Requested Shutdown - Bldg. 66 Floos 1-5 North - 7/29/96
daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Thu Jul 25 13:13:25 1996
Date: Thu, 25 Jul 1996 13:07 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU, mmahoney@MIT.EDU, schedule@MIT.EDU, lindlore@MIT.EDU
X-Envelope-To: lindlore@mit.edu, mmahoney@mit.edu, schedule@mit.edu,
shutdowns@mit.edu
X-Vms-To:
IN%"shutdowns@mit.edu, mmahoney@mit.edu, schedule@mit.edu, lindlore@mit.edu"
The following information which pertains to the requested shutdown of
Building 66 floors 1-5 North is for your review. Would you please let
me know if this is either has your approval or disapproval? I can be
contacted at 8-6651 or via return e-mail.
Thanks and I look forward to hearing from you.
Andrea Nichols
Operations Center
Building: 66 - floors 1-5 North
System: Fan supply, Air Handler 1 (PM#702536 and #702537)
Date: 7/29/96
Day: Monday
Time: 7:30 AM - 8:30 AM
Duration: 1 hour
Reason: Replace belts
Effect: Loss of supply-ventilation, supply cooling and supply-
heating in the following rooms during the one-hour shut-
down.
Rms. 125 to 165, 143, 147
Rms. 227A, 221, 225 to 265A, 243 and 247
Rms. 317, 321, 319, 325 to and including 369
Rms. 408, 421, 419, 425 to and including 471
Rms. 508 to 521B, 519, 525 to and including 571