The following information which pertains to the requested shutdown of
Building 39 - Floors 1-4 is for your review and information. Would you
please let me know either by return email or by phone (8-6651) if this
has your approval or disapproval.
Thanks and I look forward to hearing from you at your earliest
convenience.
Andrea Nichols
Operations Center
Building: 39 - Floors 1-4
System: Supply Fans
Date: July 21 PM - July 22 - AM
Day: Sunday PM - Monday AM
Time: 11:00 PM (Sunday) - 6:00 AM (Monday)
Reason: Preventive Maintenance Work
Effect: Minimal - Supply Fabns shut down one at a time for 2
hours each as follows:
PM#708550 PM#708553
Rms. 227B to 227A Rms. 238, 228A, 228,
287 to 227, 201B
Rms. 321 to 329 Rms. 301, 301A, 340T,
341Z
Rms. 421 to 427B Rms. 438 to 477
PM#708551 PM#708552
Rms. 211 to 219 Rms. 201 to 289, 240E,
240T, 201A to 259
Rms. 311 to 321A Rms. 340E, 301
Rms. 415, 415A, 415B Rms. 490, 403B, 493,
491, 487 (half), 494 and 492