The following information pertains to the requested shutdown of
Building 54. This is for your review and/or comment. Would you please
let me know if this is acceptable or unacceptable at your earliest
convenience. I can be contacted at 8-6651 or by return e-mail.
Thanks very much for your help.
Andrea Nichols
Operations Center
Building: 54
System: Chilled water supply and return
Date: 7/5/96
Day: Friday
Time: 7:00 AM - 11:00 AM
Duration: 4 hours
Reason: Must re-route electrical feed in sub-basement of Bldg.
56
Effect: No cooling for Building 54 which includes computer room
air conditioners.