Requested Shutdown - Bldg. 16, Bieman's Lab - Bldg. 56
daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Tue Jun 25 09:24:05 1996
Date: Tue, 25 Jun 1996 09:21 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU, mmahoney@MIT.EDU, schedule@MIT.EDU, karensal@MIT.EDU
X-Envelope-To: karensal@mit.edu, mmahoney@mit.edu, schedule@mit.edu,
shutdowns@mit.edu
X-Vms-To:
IN%"shutdowns@mit.edu, mmahoney@mit.edu, schedule@mit.edu, karensal@mit.edu"
The following is a requested shutdown for Bldgs. 16, and Bieman's Lab
Bldg. 56. This is for your review and information. Would you please
let me know if this acceptable or unacceptable at your very earliest
convenience. I can be reached either via e-mail or at 8-6651.
Thanks very much for your help.
Andrea Nichols
Oeprations Center
Building: 16, Bieman's Lab, Building 56
System: Chilled Water Supply and Return
Date: 6/29/96
Day: Saturday
Time: 5:00 AM - 3:00 PM
Duration: 9 hours
Reason: Tie in new chilled water piping in sub-basement
Effect: Loss of chilled water