Approved Shutdown - Bldg.66 - 6/17/96
daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Fri Jun 14 15:43:30 1996
Date: Fri, 14 Jun 1996 15:40 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU, dcarlson@MIT.EDU, cappucci@MIT.EDU, cust-coach@MIT.EDU,
gwilder%MITPPL.bitnet@mitvma.mit.edu,
bpierce%MITPPL.bitnet@mitvma.mit.edu, sdverify@MIT.EDU
X-Envelope-To: cappucci@mit.edu, cust-coach@mit.edu, dcarlson@mit.edu,
sdverify@mit.edu, shutdowns@mit.edu
X-Vms-To:
IN%"shutdowns@mit.edu, dcarlson@mit.edu, cappucci@mit.edu, cust-coach@mit.edu,
gwilder@mitppl.mit.edu, bpierce@mitppl.mit.edu, sdverify@mit.edu"
The following pertains to the approved shutdown for Bldg. 66 and is
for your information.
Thanks very much for your assistance.
Andrea Nichols
Operations
Physical Plant
Building: 66
System: Air Handlers and Supply Fans
Date: 6/16 - 17/96
Day: Sunday PM - Monday AM
Time: 11:00 PM (Sunday) - 7:00 AM (Monday)
Duration: 8 hours
Reason: Preventive maintenance work as follows:
Air Handler 1, supply fan 1 PM#702536 - services lab supply air
Air Handler 1, supply fan 2 PM#702537 -services lab supply air
Air Handler 2, PM#702539 - services primary air
Air Handler 3, PM#702541 - services interior zone
Air Handler 4, PM#702542 services sub-basement
Air Handler 5, PM#702540 services lecture hall