[33751] in Hotline Meeting
Requested Critical Shutdown - Bldg. E17, E18, E19 - 6/7 - 9/96
daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Thu Jun 6 11:52:35 1996
Date: Thu, 6 Jun 1996 11:50 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU
X-Envelope-To: shutdowns@mit.edu
X-Vms-To: IN%"shutdowns@mit.edu"
The following requested critical shutdown is for your review and
information. Would you please let me know at your eariest convenience
if this is acceptable or unacceptable. I can be contacted at 8-6651 or
via return e-mail.
Thanks.
Andrea
Operations
Critical
Building: E17, E18, E19
System: Chilled supply water and chilled water return
Date: 6/7 - 6/9
Day: Friday PM - Sunday PM
Time: 5:00 PM (6/7) - 11:59 PM (6/9)
Duration: 56 hours
Reason: To tie in the chilled water supply from the central
utility plant to the east campus
Effect: Loss of air conditioning with the exception of animal
facilities and any rooms that have mechanical or self-
contained cooling such as the switch room (telecommunications)
on E19-6th floor.