Requested Critical Shutdown - Bldg. E17, E18, E19 - 6/7 - 9/96

daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Thu Jun 6 11:52:35 1996

Date: Thu, 6 Jun 1996 11:50 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU
X-Envelope-To: shutdowns@mit.edu
X-Vms-To: IN%"shutdowns@mit.edu"

The following requested critical shutdown is for your review and
information. Would you please let me know at your eariest convenience
if this is acceptable or unacceptable.  I can be contacted at 8-6651 or
via return e-mail.

Thanks.


Andrea
Operations

Critical
Building:       E17, E18, E19
System:         Chilled supply water and chilled water return
Date:           6/7 - 6/9
Day:            Friday PM - Sunday PM
Time:           5:00 PM (6/7) - 11:59 PM (6/9)
Duration:       56 hours
Reason:         To tie in the chilled water supply from the central
                utility plant to the east campus
Effect:         Loss of air conditioning with the exception of animal
                facilities and any rooms that have mechanical or self-
                contained cooling such as the switch room (telecommunications)
                on E19-6th floor.

home help back first fref pref prev next nref lref last post