[33704] in Hotline Meeting
Requested Shutdown - Bldg. 48 - 4th floor only
daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Fri May 31 10:29:53 1996
Date: Fri, 31 May 1996 10:27 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU
X-Envelope-To: shutdowns@mit.edu
X-Vms-To: IN%"shutdowns@mit.edu"
The following is information pertaining to a requested shutdown for
building 48 - 4th floor only. Would you please advise if this is either
acceptable or unacceptable. I can be contacted at 8-6651 or by return
e-mail.
Thanks very much and I look forward to hearing from you.
Andrea Nichols
Operations Center
Building: 48 - 4th floor only
System: Reheat for Air Handler 5 Supply Duct System
Date: 6/10/96
Day: Monday
Time: 7:00 AM - 1:00 PM
Duration: 6 hours
Reason: Repair to system CVI Steam Valves
Effect: Loss of supply-heating during shutdown.