Approved Shutdown - Bldg. 7A-Rotch Library

daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Wed May 8 15:54:56 1996

Date: Wed, 8 May 1996 15:52 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: dcarlson@MIT.EDU, cappucci@MIT.EDU, shutdowns@MIT.EDU, sdverify@MIT.EDU,
        rbarlow@MIT.EDU
X-Envelope-To: cappucci@mit.edu, dcarlson@mit.edu, rbarlow@mit.edu,
 sdverify@mit.edu, shutdowns@mit.edu
X-Vms-To: 
 IN%"dcarlson@mit.edu, cappucci@mit.edu, shutdowns@mit.edu, sdverify@mit.edu, rb
   arlow@mit.edu"

The following approved shutdown is for your information.

Andrea

Building:       7A - Rotch Library
System:         Make-up air - Air Handler 1 - Equipment #712774
Date:           5/10/96
Day:            Friday
Time:           7:00 AM- 3:30 PM
Duration:       8 hours
Reason:         To relocate supply duct for ventilation.
Effect:         Loss of supply-ventilation. This does not affect
                supply-cooling or heating.