Requested Shutdown - Bldg. 13 - Roof - May 13, 1996
daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Mon May 6 09:39:58 1996
Date: Mon, 6 May 1996 09:38 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU, opsnote@MIT.EDU, mmahoney@MIT.EDU, schedule@MIT.EDU,
susang@MIT.EDU, RElices@MIT.EDU
X-Envelope-To: mmahoney@mit.edu, opsnote@mit.edu, RElices@mit.edu,
schedule@mit.edu, shutdowns@mit.edu, susang@mit.edu
X-Vms-To:
IN%"shutdowns@mit.edu, opsnote@mit.edu, mmahoney@mit.edu, schedule@mit.edu, sus
ang@mit.edu, RElices@mit.edu"
The following pertains to a requested shutdown for Bldg. 13 - Roof
is for your review and your approval/disapproval. Would you please let
me know if this is acceptable or unacceptable. I may be contacted at
8-6651 or via return e-mail.
Thanks.
Andrea
Operations Center
Building: 13 - Roof
System: Fan Exhaust Hood -#701092- rm. 1029, 701094 - roof,
701812 -east roof, 701813 - roof, 709110 - rm. 2096,
710366 - rm. 1036, 710368 - rm. 2135, 711231 - roof
east, 713551 -roof west, 713552 - roof west, 714490 -
roof, 714490 - roof, 714625 - roof, 714967- men's rm.,
715144 - roof - 715145 - roof and 715146 - roof.
Date: 5/13/96
Day: Monday
Time: 7:30 AM - 3:30 PM
Duration: 8 hours
Reason: Routine maintenance
Effect: Loss of fan exhaust hood on an individual basis.