Requested Shutdown - Bldg. 57 - 5/9-5/10/96

daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Mon May 6 08:46:19 1996

Date: Mon, 6 May 1996 08:44 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU, opsnote@MIT.EDU, mmahoney@MIT.EDU, cust-coach@MIT.EDU,
        h20coach@MIT.EDU, dmike@MIT.EDU
X-Envelope-To: cust-coach@mit.edu, dmike@mit.edu, h20coach@mit.edu,
 mmahoney@mit.edu, opsnote@mit.edu, shutdowns@mit.edu
X-Vms-To: 
 IN%"shutdowns@mit.edu, opsnote@mit.edu, mmahoney@mit.edu, cust-coach@mit.edu, h
   20coach@mit.edu, dmike@mit.edu"

Shown below is information pertaining to the requested shutdown of
Building 57 for your review.  Would you please advise at your earliest
convenience if this is acceptable/unacceptable. I may be contacted by
phone at 8-6651 or via return email.

Thank you.

Andrea
Operation Center

Building:       57
System:         Building Power
Date:           5/9 - 5/10 - 96
Day:            Thursday and Friday
Time:           11:00 PM 5/9 - 6:00 AM 5/10
Reason:         Tie-in power to new G & W switch in the sub-basement of
                Building 56.
Effect:         Loss of Building power.