[33322] in Hotline Meeting
Requested Shutdown - Bldg. 68 - All - 5/9/96
daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Fri May 3 08:48:45 1996
Date: Fri, 3 May 1996 08:44 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU, opsnote@MIT.EDU, mmahoney@MIT.EDU
X-Envelope-To: mmahoney@mit.edu, opsnote@mit.edu, shutdowns@mit.edu
X-Vms-To: IN%"shutdowns@mit.edu, opsnote@mit.edu, mmahoney@mit.edu"
The following pertains to a requested shutdown for Building 68 and is
for your review and approval/disapproval. Would you please advise it
this is either acceptable/unacceptable. I may be contacted as 8-5561 or
by return email.
Thanks.
Andrea Nichols
Physical Plant Operations
Building: 68 - All
System: Air Handler & Supply Air (PM#7115498)
Date: 5/9/96
Day: Thursday
Time: 9:00 AM - 10:30 AM
Duration: 1 1/2 hours
Reason: Filter Change
Effect: Minimal - Air Handlers 1 and 2 will be on line.