Shutdown for W91
daemon@ATHENA.MIT.EDU (JOHN NARCOTTA)
Tue Apr 30 11:43:58 1996
Date: Tue, 30 Apr 1996 11:42 EDT
From: JOHN NARCOTTA <OPCTEMP%MITPPL.bitnet@mitvma.mit.edu>
To: shutdowns@MIT.EDU, dcarlson@MIT.EDU, cappucci@MIT.EDU, sdverify@MIT.EDU
X-Envelope-To: cappucci@mit.edu, dcarlson@mit.edu, sdverify@mit.edu,
shutdowns@mit.edu
X-Vms-To:
IN%"shutdowns@mit.edu, dcarlson@mit.edu, cappucci@mit.edu, sdverify@mit.edu"
Following is information regarding a shutdown of cooling tower 1 in
W91:
*This shutdown has NO impact on building operation; cooling tower #2
*will be on-line (#1 will not be available as a backup). If #2 fails,
*work on #1 will be suspended.
Building: W91
System: Cooling tower 1 (pm# 708016), air supply-cooling
Date: 5/1/96
Day: Wednesday
Time: 8 a.m. - 2 p.m.
Duration: 6 hours
Reason: New motor needs to be covered; cover will be attached
to new motor.
Effect: No effect on building operation