Following is information regarding a scheduled routine shutdown for
building 16:

Building:       16
System:         Chilled water return and supply
Date:           5/2/96
Day:            Thursday
Time:           4 a.m. - 10 a.m.
Duration:       6 hours
Reason:         To tie in supply at 8th floor lobby area
Effect:         Loss of chilled water systems to all of 16 for
                the duration of the shutdown