[33221] in Hotline Meeting
Approved Shutdown - Bldg. 26 Room
daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Fri Apr 26 10:29:47 1996
Date: Fri, 26 Apr 1996 10:28 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU, opsnote@MIT.EDU, dcarlson@MIT.EDU, cappucci@MIT.EDU,
mmahoney@MIT.EDU, adams@mitlns.mit.edu, lindlore@MIT.EDU,
blair@mitvma.mit.edu, sdverify@MIT.EDU
X-Envelope-To: cappucci@mit.edu, dcarlson@mit.edu, lindlore@mit.edu,
mmahoney@mit.edu, opsnote@mit.edu, sdverify@mit.edu, shutdowns@mit.edu
X-Vms-To:
IN%"shutdowns@mit.edu, opsnote@mit.edu, dcarlson@mit.edu, cappucci@mit.edu, mma
honey@mit.edu, adams@mitlns.mit.edu, lindlore@mit.edu, blair@mitvma.mit.edu,
sdverify@mit.edu"
The following approved shutdown is for your information.
Building: 26 Room, #701661 - Rm. 001A, #711544 - Rm. 408, #701646
- Rm. 568, #701568 - Rm. 268, #707550 - Rm. 040, #712751
- Rm. 007.
System: Exhaust Hoods
Date: 4/29/96
Day: Monday
Time: 12 noon - 3:00 PM
Duration: 3 hours
Reason: Preventive maintenance work.
Effect: Loss of laboratory exhaust hoods on an individual basis