Apprvoved Shutdown - Bldg. 14 - Saturday, 4/27/96
daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Fri Apr 26 09:28:48 1996
Date: Fri, 26 Apr 1996 09:26 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU, opsnote@MIT.EDU, dcarlson@MIT.EDU, cappucci@MIT.EDU,
cust-coach@MIT.EDU, sdl-adm-lib@it.edu, csnyder@MIT.EDU,
sdverify@MIT.EDU
X-Envelope-To: cappucci@mit.edu, csnyder@mit.edu, cust-coach@mit.edu,
dcarlson@mit.edu, opsnote@mit.edu, sdverify@mit.edu, shutdowns@mit.edu
X-Vms-To:
IN%"shutdowns@mit.edu, opsnote@mit.edu, dcarlson@mit.edu, cappucci@mit.edu, cus
t-coach@mit.edu, sdl-adm-lib@it.edu, csnyder@mit.edu, sdverify@mit.edu"
The following approved shutdown for Building 14 is for your
information.
Building: 14 - Main Library - 1st and 2nd floors (WEST side
only)
System: Air Handler-4 and Roof Fan 4 (cooling and heating
serves west side of the library. Rms. 126, 128, 132,
134, 139, 206, 214, 216, 218, 217E, 219E, 222
Date: 4/27/96
Day: Saturday
Time: 7:00 AM - 7:00 PM
Duration: 12 hours
Reason: Replace disconnect and starter for Air Handler 4.
Effect: Loss of Air Handler 4 and Roof Fan 4,
supply-ventilation, supply-cooling and supply-heating.