[32793] in Hotline Meeting
Request for Critical Shutdown - E25
daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Mon Apr 1 10:00:03 1996
Date: Mon, 1 Apr 1996 09:59 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU, opsnote@MIT.EDU, e-zone@MIT.EDU, Rcoate@wccf.mit.edu,
Scotts@MIT.EDU
X-Envelope-To: e-zone@mit.edu, opsnote@mit.edu, Scotts@mit.edu,
shutdowns@mit.edu
X-Vms-To:
IN%"shutdowns@mit.edu, opsnote@mit.edu, e-zone@mit.edu, Rcoate@wccf.mit.edu, Sc
otts@mit.edu"
The following information pertains to the request for a critical
shutdown for E25. Please let me know either by return e-mail or call me
at 8-6651 if you forsee a problem with this.
Thanks.
Andrea
Building: E-25 - Animal Quarters
System: Air Handler 4 PM#707762 Supply Fan.
Date: 4/4/96
Day: Thursday
Time: 7:30 AM - 11:30 AM
Duration: 4 hours
Reason: Preheat coil leak (W.O.# issued to pipefitters to
repair).
Effect: Loss of supply-ventilation, cooling, heating and low
pressure steam. *Exhaust fan will be operating during
shutdown.