[32740] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Request for shutdown - Bldg. E-40

daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Wed Mar 27 09:11:40 1996

Date: Wed, 27 Mar 1996 09:11 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU
X-Envelope-To: shutdowns@mit.edu
X-Vms-To: IN%"shutdowns@mit.edu"

The following is a request for a shutdown for E-40. Would you please
advise your approval by return e-mail with a copy to IN%"sdverify@mit.edu".

Thanks and I look forward to hearing from you.

Bldg.           E40
System:         Supply Fan #707017 (Roof Supply Fan) and
                Roof Fan #707016
Date:           3/30/96
Day:            Saturday
Time:           7:00 AM - 3:00 PM
Duration:       8 Hours
Reason:         Follow up work required from original yearly
                preventive maintenance work.
Effect:         Loss of Supply-ventilation, supply cooling-core
                and exhaust - general air.


home help back first fref pref prev next nref lref last post