[32685] in Hotline Meeting
Shutdown for Bldg. 4 classrooms - 3/26/96
daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Fri Mar 22 09:27:53 1996
Date: Fri, 22 Mar 1996 09:27 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU
X-Envelope-To: shutdowns@mit.edu
X-Vms-To: IN%"shutdowns@mit.edu"
Would you please advise if the following request for a shutdown is all
right via return email or call at 8-6651.
Building: 4-145, 149, 153,055, 053, 051, 051A, 049, 047, 045, 045A
145, 149, 153, 257, 255, 253, 249, 351, 355, 357, 359,
444, 447, 449A, 449B, 454.
System: Low pressure steam system serving the radiators (& low
pressure condensate in room).
Date: 3/26/96
Day: Tuesday
Time: 7:00 AM - 3:00 PM
Duration: 8 hours
Reason: To install new steam radiator valves in each one of
the classrooms.
Effect: Loss of low pressure steam heat. *NOTE: If outside
temperatue is less than 50 degrees, shutdown will be
rescheduled.
Look forward to hearing from you and thanks.