[32580] in Hotline Meeting
Shutdowns for 3/18, 3/19 & 3/21
daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Fri Mar 15 14:03:02 1996
Date: Fri, 15 Mar 1996 14:02 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: Shutdowns@MIT.EDU, Dcarlson@MIT.EDU, Cappucci@MIT.EDU, Lambert@MIT.EDU,
Ops-note@MIT.EDU, sdverify@MIT.EDU
X-Envelope-To: Cappucci@mit.edu, Dcarlson@mit.edu, Lambert@mit.edu,
Ops-note@mit.edu, sdverify@mit.edu, Shutdowns@mit.edu
X-Vms-To:
IN%"Shutdowns@mit.edu, Dcarlson@mit.edu, Cappucci@mit.edu, Lambert@mit.edu, Ops
-note@mit.edu, sdverify@mit.edu"
The following shutdowns are for your information.
Critical
Building: W31 - 3rd floor heat
System: Heating hot water. Note:Shutdown will be rescheduled if outside
temperature is less than 40 degrees
Date: 3/18/96
Day: Monday
Time: 7:30 AM - 11:30 AM
Duration: 4 hours
Reason: Unions on converter are leaking.
Effect: No heating hot water.
Critical
Building: 68 - complete building
System: De-ionized water
Date: 3/19/96
Day: Tuesday
Time: 1:00 PM - 4:00 PM
Duration: 3 hours
Reason: To repair bad leak on system piping.
Effect: Shutdown of de-ionized water.
Building: E19
System: Hot water
Date: 3/21/96
Day: Thursday
Time: 7:30 AM - 1:30 PM
Duration: 6 hours
Reason: Tie in of new fixtures.
Effect: Loss of hot water in all ladies' and mens' restrooms
in E19.