Shutdowns for 2/26 & 2/29/96

daemon@ATHENA.MIT.EDU (JOHN NARCOTTA)
Fri Feb 23 16:11:06 1996

Date: Fri, 23 Feb 1996 16:10 EDT
From: JOHN NARCOTTA <OPCTEMP%MITPPL.bitnet@mitvma.mit.edu>
To: shutdowns@MIT.EDU, dcarlson@MIT.EDU, cappucci@MIT.EDU, sdverify@MIT.EDU
X-Envelope-To: cappucci@mit.edu, dcarlson@mit.edu, sdverify@mit.edu,
 shutdowns@mit.edu
X-Vms-To: IN%"shutdowns@mit.edu", IN%"dcarlson@mit.edu", IN%"cappucci@mit.edu",
 IN%"sdverify@mit.edu"


The following pertains to information about the shutdowns for W51 and
Building 14.

Critical
Building:       W51 (Burton-Conner House)
System:         Heating Systems
Date:           2/26/96
Day:            Monday
Time:           9:00 AM - 2:00 PM
Duration:       5 Hours
Reason:         TO REPLACE 4 RADIATOR VALVES
Effect:         Loss Of Heating Hot Water

Building:       14, Room 0330 (stack reading room).
System:         High pressure condensate, return to main
Date:           2/29/96
Day:            Thursday
Time:           5:00 PM - 12 PM
Duration:       7 hours
Reason:         To replace 10 foot section of pipe.  If outside
                temperature is 25, may not be able to do.
Effect:         Loss of steam. There will be cutting and welding. There
                may be noise and some odor.