Bldg. E25 shutdown

daemon@ATHENA.MIT.EDU (JOHN NARCOTTA)
Fri Jan 26 15:06:53 1996

Date: Fri, 26 Jan 1996 15:07 EDT
From: JOHN NARCOTTA <OPCTEMP%MITPPL.bitnet@mitvma.mit.edu>
To: shutdowns@MIT.EDU, cappucci@MIT.EDU, dcarlson@MIT.EDU
X-Envelope-To: cappucci@mit.edu, dcarlson@mit.edu, shutdowns@mit.edu
X-Vms-To: IN%"shutdowns@mit.edu", IN%"cappucci@mit.edu", IN%"dcarlson@mit.edu"

Following are notifications of upcoming shutdowns:

Building:       E25, animal quarters
System:         Heating hot water supply
Date:           1/29/96
Day:            Monday
Time:           8 a.m. - 12 p.m.
Duration:       4 hours
Reason:         To install trap
Effect:         Loss of low pressure steam, condensate returns, fire
                alarms and smoke detectors for the durationn